Service duration

Typically 1 day on-site to inspect the roll force measurement installation, evaluate and give

recommendations if further actions are needed.

During at least 4 hours, load cells and pressure plates need to be accessible outside the mill stand

for inspection and testing. This can be done during a planned maintenance stop, or by the customer

exchanging to spare load cells and spare pressure plates in the mill stand in advance.

Additional time for travel, preparation, analysis and reporting is needed.

Note: Free access to the mechanical parts and the mounting surfaces 

in the actual mechanical installation is essential for achieving

the expected goals with the Health Check during the site visit. The

accessible parts required for different load cell types and positions

in the mill stand are listed below.

The parts and mounting surfaces mentioned above need to be accessible

before the start of the work or otherwise the investigation of

them need to be planned for in advance so that it can be performed

later during the site visit.