Welcome to the official website of CNIACS Automation Technology Co., Ltd!

Woodward MSLC Master Synchronizer and Load Control Ramp Pause Contact

Ramp Pause Contact

Connect the load ramp pause switch contact to terminal 51. When closed, this

contact will hold any load ramp in progress at its current setting until the contact is opened.

Raise and Lower Set Point Contacts

Connect a center off, double-pole double-throw switch to the Raise and Lower

Load inputs, terminals 52 and 53. If the remote reference will be used, install a

second double-pole double-throw switch to simultaneously select both the Raise and Lower inputs.

Local Bus Voltage Adjustment Contacts

The Local Bus voltage adjustment contact inputs allow manual voltage control of

the operating generator’s voltages for manual paralleling. Note, if the individual

generators are in VAR/PF control, they will return to VAR/PF control as soon as

the MSLC’s raise/lower switches are returned to OFF. The switches may also be

used to change the constant generator power factor reference if operating in that mode.

Woodward MSLC Master Synchronizer and Load Control CB Aux Contact

CB Aux Contact

Connect the utility breaker auxiliary (CB Aux) contact that opens and closes

when the utility tie breaker opens and closes. Wire the breaker auxiliary contact

in series between the +24 Vdc voltage source and terminal 47 of the MSLC. In

addition, it may be desirable to put an MSLC ON/OFF switch in series with this input.

Utility Unload Contact

Connect the utility unload switch to terminal 48.

Import/Export Control Contacts

The import/export mode of control is initiated by closing the CB Aux contact 47

and closing the import/export contact 49.

Process Control Mode Contact

If the MSLC will be used as a process control, connect a switch from +24 Vdc to

the Process Control discrete input, terminal 50. When this contact is closed, load

on the associated DSLC™ equipped generators in isochronous load sharing is

controlled at a level required to maintain the analog process input at a chosen reference.

Woodward MSLC Master Synchronizer and Load Control Discrete Inputs

Discrete Inputs

The discrete inputs are the switch input commands to the MSLC. Discrete inputs

are optically isolated from the control and require 10 mA at 24 Vdc each to

activate. Discrete inputs may be powered by the same source as control power.

All contacts used in the discrete circuits should be the isolated dry contact type to

work properly with the low currents used in these circuits.

Connect the 24 Vdc supply common (–) to terminal 43. Route +24 Vdc through

the appropriate external contact to the discrete input.

Synchronizer Mode Switch

The synchronizer mode switch (single-pole, four-position) controls the operating

mode of the synchronizer. The switch must be wired to terminals 44. 45. and 46.

as shown in Figure 1-3. The four positions are Off, Check mode, Permissive

mode, and Run mode. When the switch is off, the synchronizer is out of operation.

Woodward MSLC Master Synchronizer and Load Control Process Control

Process Control

A process controller is provided for cogeneration, fluid level maintenance,

pressure control, or other applications. An adjustable bandwidth signal input filter,

flexible PID controller adjustments, an adjustable deadband, and control

selectable for direct or indirect action, allow the process control to be used in a

wide variety of applications.

A 4–20 mA (1–5 Vdc or a 4–12–20 mA) process transmitter provides the process

signal to the MSLC. The MSLC includes an internal digital process reference

which may be controlled by the raise and lower switch contact inputs or by an

external 4–20 mA (1–5 Vdc) remote process reference. The output of the

process control, like the import/export control, is the percentage of rated load

setpoint to the individual generators in isochronous load sharing.

An adjustable ramp allows smooth entry and exit from the process control mode.

When the process control mode is selected, the load reference is ramped in a

direction to reduce the error between the process input and the process

reference. When the error is minimized or the reference first reaches either the

high or low specified pull-in limits, the process controller is activated. When the

load reference output reaches either 100% or 0%, the control will maintain that

load reference until process control is established. The MSLC is not capable of

overloading or reverse powering in order to attempt to meet the process

reference. The high and low limit switches mentioned above can be used to

indicate that either too many or too few generators are on-line to maintain the

process within its limits.

Woodward MSLC Master Synchronizer and Load Control Integrating control

The import/export control is an integrating control. It adjusts the percentage of

rated load carried by the individual generators, operating in isochronous load

sharing, in order to maintain a set import/export or base load level. The MSLC

will therefore maintain a constant base load or import/export level even with

changing utility frequencies. The MSLC provides switch inputs to allow raising or

lowering the internal digital base load or import/export reference. The control also

provides a 4–20 mA (1–5 Vdc) analog input for remote reference setting, if desired.

The MSLC is equipped with a Utility Unload switch, which provides an adjustable

time controlled ramp to lower the base load or import/export level. When the level

is below an adjustable threshold, the MSLC issues a breaker open command to

separate the utility from the local bus. Again, the ramp pause switch can be used

to stop the utility unload at any point. The maximum load that the MSLC can tell

the individual generators to carry is their rated loads. So, in the event that the

plant load is greater than the capacity of the operating generators, the utility

unload will stop when 100% rated load is reached on each of the operating

generators. This prevents accidental overloading of the local generators when a

reduced number are on line.

The MSLC also includes two adjustable load switches which can be used for

external functions or warnings when chosen system load levels are attained. The

high and low limit switches may also be activated when 100% or 0% base load

signal to the generators is reached.

Woodward MSLC Master Synchronizer and Load Control Load Control

Load Control

The load control uses digital signal processing techniques to provide significantly

improved accuracy and speed of response over conventional analog

measurement techniques. Accuracy is improved because the instantaneous

measurement of the voltage and current signal wave forms allows true RMS

measurement. Measuring true RMS power allows optimal load control in parallel

applications even in the presence of power line distortions. This method provides

faster response time because it eliminates the long integration times required in

analog circuits. Measurement speed is particularly important in power control

applications where rapid response to load and speed changes is essential.

Load control begins at breaker closure when the MSLC takes control of the

system load. The system load immediately prior to breaker closure is used as the

starting base load. On command, the adjustable ramp allows smooth, time

controlled loading into a set import/export level. A ramp pause switch is provided

to stop the ramp at any point.

Woodward MSLC Master Synchronizer and Load Control Synchronizer

Synchronizer

The MSLC uses digital signal processing techniques to derive both true RMS

voltages and relative phase angles of the fundamental frequencies of the utility

and the local bus voltage wave forms. Digital signal processing techniques offer

significantly improved measurement accuracy in the presence of wave form

distortions, particularly since the phase measurement does not depend on zero

crossings of the voltage wave forms.

Either phase matching or slip frequency synchronizing may be selected. Phase

matching provides rapid synchronizing for critical standby power applications.

Slip frequency synchronizing ensures that the initial flow of power will be either

out of the local system (export) or into the local system (import), depending on

whether a positive or negative slip is chosen. For both synchronizing methods,

the MSLC uses actual slip frequency and breaker delay values to anticipate an

adjustable minimum phase difference between the utility and the local bus.

Additional synchronizer functions include voltage matching, time delayed

automatic multi-shot reclosing, auto-resynchronizing, and a synchronizer timeout

alarm. Each of these features may be enabled or disabled during setup.

Woodward MSLC Master Synchronizer and Load Control Functions

MSLC functions include:

 Selectable for phase matching or slip frequency synchronizing between the

utility and a local bus with voltage matching;

 Automatic system loading and unloading for bumpless load transfer;

 Import/Export level control capability;

 Process control for cogeneration, pressure, maintenance, or other process;

 Proportional loading of associated DSLC controls in isochronous load sharing;

 Adjustable Power Factor control;

 Built in diagnostics with alarm relay driver output;

 Multi-function adjustable high and low limit alarms and adjustable load

switches with relay driver outputs;

 Digital communications network to provide loading and power factor control

of individual DSLC equipped generators;

 Full setup, metering, and diagnostic capability through a hand held

programmer terminal (Figure 1-2).

Introduction

This manual describes the Woodward MSLC Master Synchronizer and Load Control.

Application

The MSLC is a microprocessor-based overall plant load control designed for use

in a system with Woodward DSLC™ (Digital Synchronizer and Load Control)

controls on each generator to provide utility synchronizing, paralleling, loading,

and unloading of a three-phase generating system.

Woodward MSLC Master Synchronizer and Load Control Application

Introduction

This manual describes the Woodward MSLC Master Synchronizer and Load Control.

Application

The MSLC is a microprocessor-based overall plant load control designed for use

in a system with Woodward DSLC™ (Digital Synchronizer and Load Control)

controls on each generator to provide utility synchronizing, paralleling, loading,

and unloading of a three-phase generating system.

MSLC functions include:

 Selectable for phase matching or slip frequency synchronizing between the

utility and a local bus with voltage matching;

 Automatic system loading and unloading for bumpless load transfer;

 Import/Export level control capability;

 Process control for cogeneration, pressure, maintenance, or other process;

 Proportional loading of associated DSLC controls in isochronous load sharing;

 Adjustable Power Factor control;

 Built in diagnostics with alarm relay driver output;

 Multi-function adjustable high and low limit alarms and adjustable load

switches with relay driver outputs;

Woodward Digital Synchronizer and Load Control (DSLC) SPECIFICATIONS

SPECIFICATIONS

EENNVVIIRROONNMMEENNTTAALL

SSPPEECCIIFFIICCAATTIIOONNSS

Operating Temperature…………………………………………-40 to +70 °C (-40 to +158°F)

Storage Temperature…………………………………………….-55 to +105 °C (-67 to +221°F)

Humidity………………………………………………………………95% at 38 °C

Electromagnetic Susceptibility………………………………..ANSI/IEEE C37.90.2; ANSI C37.90.1-1989

Mechanical Shock………………………………………………..US MIL-STD 810C, Method 516.2. Procedures I, II, V

Vibration………………………………………………………………US MIL-STD 167. Type I

EELLEECCTTRRIICCAALL

SSPPEECCIIFFIICCAATTIIOONNSS

CCoonnttrrooll

PPoowweerr

SSuuppppllyy

IInnppuutt

Operating…………………………………………………………….8–32 Vdc continuous (as low as 10 Vdc, 1.8 A max, or as high

as 77 Vdc for up to 5 min)

Reverse………………………………………………………………..-56 Vdc continuous

Burden………………………………………………………………..18 W, 1 A max.

VVoollttaaggee

SSeennssiinngg

IInnppuuttss

VVoollttaaggee::

120 Vac Input (L-N) Wye PT Configuration………………..65–150 Vac, terminals 4-5. 7–12. 9 –12. and 11–12

240 Vac Input (L-N) Wye PT Configuration………………..150–300 Vac,  terminals 3-5. 6–12. 8–12. and 10–12

120 Vac Open Delta PT Configuration……………………..65–150 Vac, terminals 3-5. 6–8. 8–10 and 10–6

240 Vac Open Delta PT Configuration……………………..150–300 Vac, terminals 3-5. 6–8. 8–10. and 10–6

Phases ………………………………………………………………..Three phase generator bus, single phase parallel bus

Frequency …………………………………………………………..45–66 Hz

Burden………………………………………………………………..Less than 0.1 VA per phase

Accuracy…………………………………………………………….0.1% of full scale

CCuurrrreenntt

IInnppuuttss

Current………………………………………………………………..0–5 A rms

Frequency …………………………………………………………..45 to 66 Hz

Burden………………………………………………………………..Less than 0.1 VA per phase

Accuracy…………………………………………………………….0.1% of full scale

Phases ………………………………………………………………..Three phase generator bus

Discrete Inputs ……………………………………………………..18–40 Vdc @ 10 mA

Relay Driver Outputs………………………………………………18–40 Vdc @ 200 mA sink

Analog Inputs……………………………………………………….4–20 mA @ 243Wor 1-5 Vdc @ 10kW

Local Operating Network……………………………………….Echelon®LonWorksTMTechnology, Standard Protocol, 1.25 MBPS

Calibration and Diagnostics Port …………………………….RS422

CCOOMMPPLLIIAANNCCEE

UL/cUL………………………………………………………………….Listed

Search for products

Back to Top
Product has been added to your cart