EXAMPLE 2 – COGENERATOR CONTROL
Given that a co-generation system has automatic
engine controls, auto synchronizer, and automatic kW
and kVar controls, the system will virtually operate by
itself. The only functions not readily apparent are the
start/stop signals to the generators. Two system con
figurations using a Power Relay may be utilized to
generate contact closures for start and/or stop signals.
The first configuration (Figure 2) shows a power relay
connected to the utility to sense kW. The pickup point of
the relay is set at the maximum desired utility power
level. If the power relay contact closes, the generator
will be started and automatically paralleled with the
utility system. A time delay of 15 seconds or more is
generally included in the start circuit to ignore
transient overload conditions.